    RA Bill Format for Construction in India: How Running Bills Work

    Aryavrut Team Published: Nov 22, 2026 8 min read

    What a running account (RA) bill is, what goes into it, the deductions to show, a section-by-section format you can copy, and the mistakes that delay contractor payments.

    On most construction contracts in India, a contractor is not paid once at the end. They are paid in stages, through running account bills, usually called RA bills. Each RA bill claims payment for the work done so far, measured against the bill of quantities (BOQ). When an RA bill is wrong or incomplete, payment stops while it goes back and forth between site and office.

    This guide explains what an RA bill contains, how to prepare one, and a format you can copy.

    What an RA bill is

    An RA bill is an interim bill. It records the quantity of each BOQ item executed up to a date, values it at the contract rate, and claims the difference from what was already paid. Bills are numbered in sequence: RA-1, RA-2, RA-3, and so on. When the work is complete, the last bill is the final bill, which settles every quantity, variation and recovery.

    The key idea is that RA bills are cumulative. Each bill shows the quantity executed up to date, the quantity already billed in previous bills, and the quantity claimed in this bill. Working cumulatively means a mistake in one bill gets caught and corrected in the next, instead of being carried forward forever.

    What goes into an RA bill

    An RA bill has three parts: the header, the abstract of work done, and the deductions.

    The header

    • Name of the work and location
    • Work order or agreement number and date
    • Client and contractor names, addresses and GSTINs
    • RA bill number and the period it covers
    • Date of the last measurement

    The abstract of work done

    For each BOQ item, the abstract lists:

    1. Item number and description, exactly as in the BOQ
    2. Unit (cum, sqm, rmt, kg, nos)
    3. BOQ quantity and contract rate
    4. Quantity executed up to the previous bill
    5. Quantity executed in this period
    6. Cumulative quantity up to date
    7. Amount up to the previous bill, amount for this bill, and cumulative amount

    Extra items and approved variations are listed separately, with a reference to the approval, so the client can check them against the order that allowed them.

    Deductions and recoveries

    What is deducted depends on the contract, so read the agreement before the first bill. The common ones are:

    • Retention money — a percentage held back until the defect liability period ends, as set in the contract
    • Mobilisation advance recovery — instalments of any advance paid at the start
    • Material issued by the client — cement, steel or other material supplied by the client and recovered at the agreed rate
    • Security deposit — where the contract collects it through running bills
    • TDS — tax deducted on payments to contractors, at the rate that applies to the contractor
    • Labour welfare cess — where the work falls under the building and other construction workers cess

    GST is added to the bill at the rate that applies to your works contract. Check the rate and the place of supply with your accountant, especially for government work.

    An RA bill format you can copy

    Lay the bill out in this order. It works in a spreadsheet or on paper.

    1. Cover sheet: name of work, agreement number, RA bill number, period, gross amount, total deductions, net payable
    2. Abstract: one row per BOQ item with the columns listed above, then extra items and variations
    3. Deduction sheet: each recovery with its basis, the amount this bill and the amount recovered to date
    4. Tax sheet: taxable value, GST, TDS
    5. Measurement references: the measurement book page for every quantity claimed
    6. Supporting documents: site photos, test reports, approved drawings, delivery challans for material
    7. Certification: signatures of the site engineer, the client's engineer and the contractor

    How to prepare an RA bill, step by step

    1. Measure the work on site with the client's engineer, and record each measurement in the measurement book (MB) with the date, location and dimensions.
    2. Check each measurement against the BOQ item and the latest approved drawing.
    3. Work out the cumulative quantity to date for each item, then subtract the quantity already billed to get this bill's quantity.
    4. Apply the contract rate to the cumulative quantity and to this bill's quantity.
    5. List extra items and variations separately, each with its approval reference.
    6. Apply the deductions and recoveries the contract allows, and show how each one was worked out.
    7. Add GST, then work out the net amount payable.
    8. Attach MB references, photos and test reports, and get the bill certified.
    9. Submit the bill and track it until payment, noting any items the client disallows so they can be resolved before the next bill.

    Mistakes that delay payment

    • Quantities above the BOQ without an approved variation — the client's engineer will hold the whole bill, not just the item
    • Arithmetic errors in cumulative figures — one wrong "previous bill" figure breaks every bill after it
    • Missing measurement book references — a quantity without an MB page is easy to disallow
    • Recoveries that don't match the contract — retention or advance recovery worked out on the wrong base
    • No photos or test reports — especially for work that gets covered up, like reinforcement or plumbing in walls

    Doing RA bills in software

    Most of these mistakes come from copying figures between registers, spreadsheets and WhatsApp messages. When measurements, the BOQ and previous bills sit in one system, the cumulative figures calculate themselves and every quantity links back to its measurement.

    That is what we built ProjectSathi for. It is a civil site management system for Indian construction teams that covers BOQ and invoice automation, site attendance, materials and payroll, and it works offline at remote sites. You can read more about it on our ProjectSathi page.